PROJECT NUMBER: 1810-30
PROJECT TITLE: CLEARANCE WORKS
DATE: September 2018
DURATION: 3 weeks
RELATION TO THIS PROJECT: Project 5 was to carry out emergency tree works across Perth and Kinross, works included large dangerous trees/ attending wind blow/ traffic management and tree removal from Perth Crematorium.
SCOTFAST are part of the Greenspace Framework for PKC, this includes tree works and emergency tree works. The Client made contact with SCOTFAST following strong winds to assist with opening school routes, opening blocked roads and clearing Perth Crematorium.
SCOTFAST has a reputation for responding quickly and providing a high standard of service.
Responding within 1 hour of the initial phone call with one team made up of three trained chainsaw operators and a 4×4 vehicle.
Works included temporary signage or road closures to allow works to be carried out.
The Client then made a request for further teams to assist in clearing and if we could visit the Perth Crematorium knowing that SCOTFAST has access to large scale plant and the experience to offer large clearance solutions.
SCOTFAST made available a further two teams of three chainsaw operators and a 4×4 vehicles that carried out works on shifts through the first three nights. Including temporary lighting towers and traffic management.
SCOTFAST after visiting the Perth Crematorium, attended site with a Forestry Forwarder, Allstor, Norcar 4AT, Kubota 3 tonne excavator with grab and a Valtra fitted with Awhi Mulcher to carry out clearance works.
SCOTFAST assisted the Client for three weeks in total with over 14 chainsaw operators, various plant including a TigerCat to move an oversized tree that had fallen above Blairgowrie.
SCOTFAST have been highly recommended by the Client to other authorities for out great communication and high quality of finish left on all our sites.